Saturday, July 27, 2024

Hull City Council weekly traffic and travel update – 17 May – Hull CC News

Must read

Here is the latest breakdown of scheduled and emergency works taking place across Hull over the next few weeks. All works are subject to change. For the latest updates:

Location Start date Due date Summary of works Utility/HCC
A63 improvement scheme – St James Street to Market Place 01-May-20 01-May-25 Major A63 Improvement scheme – full infrastructure change. Lane and road closures until completion of scheme. National Highways
A63 Castle Street 30-Apr-24 24-May-24 Overnight closures on the A63. To find our more, visit https://nationalhighways.co.uk/our-roads/yorkshire-and-north-east/a63-castle-street/ National Highways
A63 – Queen Street 13-May-24 12-Jul-24 Castle Street improvement scheme. Full closure of the Queen Street westbound exit slip road. Full diversion route will be in place. National Highways
Argyle Street 16-May-24 22-May-24 Service box replacement outside Hull Royal Infirmary (opposite entrance to hospital car park). Lane closure in place. Northern Powergrid
Anlaby Road 17-May-24 23-May-24 Repair leaking water supply pipe outside number 734. Lane closure in place, Yorkshire Water
Beverley Road 13-May-24 24-May-24 Utility maintenance/upgrade between Strand Close and Harley Street. Lane closure in place. Northern Gas Network
Chamberlain Road 13-May-24 31-May-24 Works at the junction of Simpson Crescent. S278
Great Union Street 29-May-24 30-May-24 Replacing all signals heads at the junction of St Peter Street. Multi-way signals in place. Hull City Council (Traffic Signals)
Hall Road 21-May-24 23-May-24 Remedial Works from the junction of Hall Road and Milldane to the junction of Hall Road and Danepark Road. Multi-way signals in place. Connexin
Holderness Road 20-May-24 31-May-24 Works to install column, cabinets and cameras. Works on Holderness Road in two locations approaching the junction near to Cornmill hotel and near to DW Sports Fitness. Lane closure in place between 9.30am and 3.30pm. Hull City Council
Micro-surfacing programme 29-Apr-24 24-May-24 Various road closures across the city for the annual micro-surfacing programme. For more information, visit https://news.hull.gov.uk/22/04/2024/hull-city-council-announces-micro-surfacing-programme-for-30-streets/. Hull City Council (Major Projects)
Mount Pleasant 28-May-24 29-May-24 Telecoms installation opposite The Car Lot. Two-way signals in place from 8pm to 6am. Hutchison 3G
Moorhouse Road 11-Mar-24 14-Jun-24 Installing a new pipe and manhole on the carriageway and connecting onto the combined sewer. Part of the Living with Water Aqua Green Scheme. Road closure in place. Yorkshire Water
National Avenue 03-May-24 19-May-24 Utility connections at the junction of Harpings Road. Multi-way signals in place. Northern Gas Network
Preston Road 13-May-24 25-May-24 Complete high voltage connection from Preston Road east of Harpham grove junction across Preston Road into central verge reservation. Lane closure in place. The Electricity Network Company
Walker Street 06-May-24 28-Jun-24 Essential carriageway repairs from Rawling Way to Quantock Close. Road closure in place. Hull City Council (Major Projects)

Latest article